Coordination in construction is often discussed as a technical task, but in reality, it is a risk-management tool. Without proper coordination, even the best designs can turn into delays, redesigns, and frustration on site.
During my work on the Kempinski Gold Coast Building in Accra, Ghana, I experienced firsthand how poor or unclear coordination can multiply problems instead of solving them. This project became a real lesson in why coordination must be taken seriously—technically, contractually, and professionally.
The architectural scope alone involved multiple parties:
The initial concept was developed by an American architectural firm.
Our company, was responsible for developing the drawings.
Page appointed a separate interior design subcontractor.
Kempinski had its own standards and its own architect.
That makes four architectural parties working on the same scope.
In addition to that, the project included:
Structural engineers
Post-tension (PT) designers
MEP engineers
Façade subcontractors
Without strong coordination, conflicts were inevitable.
As the engineer leading this part of the project, I quickly realized something important:
Coordination is not only about solving clashes—it is about protecting yourself as an engineer.
When responsibilities are not clearly defined, coordination naturally falls on the site or project engineer. Every architectural opinion came with design changes, and each change cost at least one week of redesign, reviews, and re-approval with other disciplines.
At one stage, the Kempinski architect requested the addition of a new slab inside a double-height space.
This single request triggered a chain reaction:
Structural analysis to verify if new columns could be introduced
Coordination with the PT engineer
Design changes including:
Two drop beams in the basement
Two new columns in the ground floor
Creation of a new technical floor
Once we moved to 3D modeling, another issue appeared:
The new slab interfered with the main entrance interior design.
As a result:
Slab limits had to be modified
Structural and PT calculations were repeated
All drawings were re-coordinated again
Adding the slab created two critical levels:
One at 2.80 m
One technical level at 2.50 m, which was insufficient
At this stage, MEP coordination became the main challenge:
HVAC ducts
Firefighting systems
Electrical trays
Plumbing networks
The final ceiling height depended entirely on MEP requirements.
After long coordination meetings, a major decision was made:
The VRV ducted system was removed
Split units were used instead
The slab was left exposed, with no false ceiling
Technically and coordinationally, the solution worked—and it was approved.
After all this effort:
The client was not satisfied with the final appearance
Design changes were requested again
The slab became visible in the ground floor and affected the interior concept
Even after execution, further changes were requested by the owner.
All previous work—design, coordination, approvals—had to be reconsidered.
The key takeaway from this experience is simple:
Coordination must be documented.
It is not enough to agree verbally or assume alignment.
Proper coordination requires:
Written emails
Approved and signed drawings
Clear responsibilities
Final decisions before construction starts
Because in construction, while variation orders (VOs) may bring additional payment, they almost always:
Delay the project
Increase pressure on site
Drain time and energy
Affect overall performance
In most cases, the money does not compensate for the loss.
Building is easy.
Changing what was already built is what destroys projects.
Coordination is the backbone of construction—almost 80% of your work depends on it.
Building Maintenance
04 08 2026
0 Code Compliance in Renovations: A Contractor's Guide to Permits, Inspections, and Modern Building StandardsNavigating building codes for renovation is crucial for any contractor. This guide covers the entire process, from identifying applicable codes and securing permits to managing inspections and understanding the severe consequences of non-compliance.
Real Estate
04 08 2026
0 From Supercars to Penthouses: Why Automotive and Fashion Brands Are Entering the Luxury Real Estate MarketA powerful new trend is reshaping the ultra-luxury market: the rise of non-hotel branded residences. This strategic analysis explores why iconic automotive and fashion brands are entering the property market, offering key insights for developers and brand strategists on this evolution in experiential marketing.
Excavation, Shoring and Dewatering
03 08 2026
0 Urban vs. Mountain Tunneling: How TBMs Conquer Vastly Different Ground ChallengesDiscover the profound differences between tunneling beneath a city and through a mountain. This analysis covers the distinct TBM tunneling challenges, from managing ground settlement in urban areas to battling rockbursts and water ingress in mountains.
Real Estate
03 08 2026
0 Beyond the Giga-Project: A Developer's Guide to Capturing Ancillary Real Estate OpportunitiesAstute developers know the real value of a giga-project lies in its supporting ecosystem. This guide provides a strategic framework for identifying and executing profitable ancillary real estate development, from logistics hubs to workforce housing, to build a resilient, high-demand portfolio.
Real Estate
02 08 2026
0 Unlocking the Black Box: How Zillow Gave Real Estate Data to the PeopleBefore Zillow, critical property information was a closely guarded secret of real estate agents. This article explores how Zillow's strategy of data democratization unlocked this 'black box,' empowering consumers and forever changing the roles of buyers, sellers, and agents.
Construction Building Rehabilitation
02 08 2026
0 Strengthening the Core: A Practical Guide to Seismic Retrofitting for Existing BuildingsOlder buildings often lack modern seismic resilience, posing significant risks. This guide explores the critical process of seismic retrofitting, from initial structural assessment to the implementation of key strengthening techniques like steel moment frames and foundation bolting, ensuring long-term safety and stability.
1 Comments
Amon Abubakar-Sediq Kotei
02 Jan 2026I’ve learnt as a construction student that coordination is the unseen backbone of every project.Good coordination aligns engineers, supervisors, artisans, and suppliers, turning plans on paper into structures on site. Without it, structures may rise, but efficiency collapses.
Submit Comment